What Is Rate Analysis? | Rate Analysis For Brickwork, Earthwork, Concrete & Plaster

Posted on 01/06/2023 by CivilEngineerDK

 

Introduction

Rate analysis is the process of estimating the cost of construction projects by breaking down the cost of each item into its components, such as materials, labor, and overheads, and calculating the cost per unit of measurement. This helps in determining the most cost-effective way of completing the project and preparing accurate cost estimates.

There are various types of rate analysis for different construction activities, such as brickwork, earthwork, concrete, and plaster. In this blog, we will discuss each type of rate analysis along with calculation tables.

Rate Analysis for Brickwork:

Brickwork involves laying bricks in a specific pattern with the help of cement mortar. Rate analysis for brickwork involves calculating the quantity of bricks required, the quantity of cement and sand required for the mortar, and the labor cost involved.

The following table shows a sample calculation for the rate analysis of brickwork:

ItemUnitQuantityRate (Rs.)Amount (Rs.)
BricksNos.10005.005000.00
CementBags10350.003500.00
SandNos.2.51200.003000.00
LaborDay51000.005000.00
Total16500.00

The unit of measurement for brickwork is usually square feet. The rate per square foot is calculated by dividing the total cost of materials and labor by the total area of brickwork.

Rate Analysis for Earthwork:

Earthwork involves excavation and filling of soil for the construction of foundations, retaining walls, and other structures. Rate analysis for earthwork involves calculating the volume of earth to be excavated or filled, the cost of transportation of the earth, and the labor cost involved.

The following table shows a sample calculation for the rate analysis of earthwork:

ItemUnit QuantityRate (Rs.) Amount (Rs.)
ExcavationCu.M.100100.0010000.00
FillingCu.M.5050.002500.00
TransportationTon10500.005000.00
LaborDay101000.0010000.00

The unit of measurement for earthwork is usually cubic meters. The rate per cubic meter is calculated by dividing the total cost of materials and labor by the total volume of earthwork.

Rate Analysis for Concrete:

Concrete is a mixture of cement, sand, and coarse aggregates, and is used for the construction of foundations, columns, beams, and slabs. Rate analysis for concrete involves calculating the quantity of cement, sand, and aggregates required, and the labor cost involved.

The following table shows a sample calculation for the rate analysis of concrete:

ItemUnitQuantityRate (Rs.)Amount (Rs.)
CementBags10040040,000
SandCu.M.21,5003,000
Coarse AggregateCu.M.42,0008,000
WaterLtr.5000.2100
LaborDay5300015,000
Total66,100

The unit of measurement for concrete is usually cubic meters. The rate per cubic meter is calculated by dividing the total cost of materials and labor by the total volume of concrete.

Rate Analysis for Plaster:

Plaster is a layer of cement or gypsum applied on walls and ceilings to provide a smooth surface. Rate analysis for plaster involves calculating the quantity of cement, sand, and water required, and the labor cost involved.

The following table shows a sample calculation for the rate analysis of plaster:

Item UnitQuantityRate (Rs.) Amount (Rs.)
CementBags10350.003500.00
SandCu.M.21200.002400.00
WaterLtr.10000.2200.00
LaborDay31000.003000.00
Total9,100

 

The unit of measurement for plaster is usually square meters. The rate per square meter is calculated by dividing the total cost of materials and labor by the total area of plaster.

Conclusion🎯

In conclusion, rate analysis is an essential part of construction cost estimation. By calculating the cost of each component of the construction project, it helps in determining the most cost-effective way of completing the project. The tables above provide a sample calculation for each type of rate analysis, but it is important to note that actual rates may vary depending on the location, availability of materials, and other factors.

 

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Categories

  • architecture
  • building
  • Building Material
  • Civil engineering
  • civil engineering software
  • construction
  • foundation
  • Geotechnical Engineering
  • Highway Engineering
  • Reinforcement
  • Road
  • Surveying

Archives

  • June 2025
  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • August 2024
  • July 2024
  • June 2024
  • May 2024
  • April 2024
  • March 2024
  • February 2024
  • January 2024
  • November 2023
  • October 2023
  • September 2023
  • August 2023
  • July 2023
  • June 2023
  • May 2023
  • April 2023

Connect me on 👇

  • Instagram
  • Facebook
  • YouTube
  • Telegram
  • LinkedIn
  • X
©2025 Civil Engineer DK | Design: Newspaperly WordPress Theme